Given a cost difference of $16,000 and a slope coefficient of 0.40, what is the corresponding difference in machine hours?

Multiple choice question for Cost Function and Behavior. Select an option, then review the explanation below.

Choose the correct answer

Explanation

To find the difference in machine hours, divide the cost difference by the slope coefficient: $16,000 ÷ 0.40 = $40,000. Therefore, the correct answer is option D.

Practice related questions from the same subject.

  1. 1.How is the connection between specific cost elements and their cost drivers characterized within a dependent variable cost pool?
  2. 2.Which technique uses the minimum and maximum values of the cost driver and associated costs within the relevant range to estimate costs?
  3. 3.Given that the unexplained variation is 350,050 and the total variation amounts to 700,505, what is the coefficient of determination?
  4. 4.What term describes the scenario where multiple independent variables exhibit a strong correlation with each other?
  5. 5.In regression analysis, given an actual cost of 85 and an error term of 25, what is the predicted cost value?

PakQuizHub — free MCQs and past papers for Pakistan government job tests. Content is for educational practice only.

If the difference in costs is $16000 and the slope coefficient is 0.40, then difference in machine hours would be __________? - PakMcqs | PakQuizHub