Direct Cost Variances and Management Control

PPSCFPSCNTSPakistan govt jobs
Subject
Direct Cost Variances and Management Controlaccounting-mcqs › cost-accounting-mcqs › direct-cost-variances-and-management-control
Published
9 May 2023
Last updated
28 May 2026

Browse all Direct Cost Variances and Management Control MCQs

Given a static budget variance of $38,000 and a static budget value of $12,000, what is the actual outcome?

Multiple choice question for Direct Cost Variances and Management Control. Select an option, then review the explanation below.

Choose the correct answer

Explanation

The actual result is calculated by adding the static budget amount ($12,000) to the static budget variance ($38,000), which equals $50,000.

Practice related questions from the same subject.

  1. 1.Within the hierarchy of costing and budgeting, which of the following represents a product sustaining cost?
  2. 2.Given that the actual cost of a material is $700 while the planned cost was $900, what type of variance is observed?
  3. 3.Given that the actual outcome is $65,000 and the static budget variance amounts to $35,000, what is the value of the static budget?
  4. 4.What term is used to describe the anticipated performance of a company?
  5. 5.Given that the actual labor cost is $1200 while the planned labor cost is $1000, what is the nature of the labor price variance?

PakQuizHub — free MCQs and past papers for Pakistan government job tests. Content is for educational practice only.

If the static budget variance is $38000 and the static budget amount is $12000, then an actual result would be _____________? - PakMcqs | PakQuizHub