Given a budgeted total of 4,550 direct labor hours and a labor cost rate of $600 per hour, what is the total direct labor cost?

Multiple choice question for Job Costing. Select an option, then review the explanation below.

Choose the correct answer

Explanation

To find the total direct labor cost, multiply the number of labor hours (4,550) by the cost per hour ($600). The calculation is 4,550 × $600 = $2,730,000.

Practice related questions from the same subject.

  1. 1.Given that the planned direct labor hours amount to 3,550 and the labor cost rate is $500 per hour, what is the total direct labor expense?
  2. 2.What term describes the scenario where a cost object is associated with a specific job, customer, or product?
  3. 3.In normal costing, what is determined by multiplying the budgeted overhead rate by the actual quantity of the allocation base used?
  4. 4.Given an indirect cost pool budget of $139,600 and a total cost allocation base amounting to $155,600, what is the budgeted indirect cost rate?
  5. 5.Given a budgeted indirect cost rate of $225 and a budgeted allocation base of 750 hours, what is the total annual budgeted indirect cost?

PakQuizHub — free MCQs and past papers for Pakistan government job tests. Content is for educational practice only.

If the budgeted direct labor hours are 4550 and direct labor cost rate is $600 per labor hour then, total direct labor cost would be _____________? - PakMcqs | PakQuizHub