Given that the planned total direct labor hours amount to 5,500 and the expected direct labor expense is $755,000, what is the budgeted direct labor cost rate per hour?

Multiple choice question for Job Costing. Select an option, then review the explanation below.

Choose the correct answer

Explanation

To find the budgeted direct labor cost rate, divide the total budgeted direct labor cost ($755,000) by the total budgeted labor hours (5,500). This calculation results in $137.27 per labor hour.

Practice related questions from the same subject.

  1. 1.Given that the planned direct labor hours amount to 3,550 and the labor cost rate is $500 per hour, what is the total direct labor expense?
  2. 2.What term describes the scenario where a cost object is associated with a specific job, customer, or product?
  3. 3.In normal costing, what is determined by multiplying the budgeted overhead rate by the actual quantity of the allocation base used?
  4. 4.Given an indirect cost pool budget of $139,600 and a total cost allocation base amounting to $155,600, what is the budgeted indirect cost rate?
  5. 5.Given a budgeted indirect cost rate of $225 and a budgeted allocation base of 750 hours, what is the total annual budgeted indirect cost?