Water flows through four connected tanks and is heated along the way, as illustrated. To implement a cascade control system that regulates the temperature of the water exiting tank 4, considering a disturbance in the temperature of a secondary stream entering tank 2, where is the optimal location for the secondary measurement in the inner control loop?

Process Control and Instrumentation MCQs for PPSC, FPSC, NTS, and Pakistan government job tests. Select an option below, then read the explanation.

PPSCFPSCNTSPakistan govt jobs
Subject
Process Control and Instrumentationchemical-engineering › process-control-and-instrumentation
Published
5 Mar 2019
Last updated
28 May 2026

Browse all Process Control and Instrumentation MCQs

Choose the correct answer

Explanation

For cascade control, the secondary measurement should be taken at tank 3, which is immediately downstream of tank 2 where the disturbance occurs. This allows the inner loop to quickly respond to changes before the final temperature at tank 4 is affected.