What parameter is primarily measured during a transformer's no-load test?

Transformers MCQs for PPSC, FPSC, NTS, and Pakistan government job tests. Select an option below, then read the explanation.

PPSCFPSCNTSPakistan govt jobs
Subject
Transformerselectrical-engineering-mcqs › transformers
Published
28 Jun 2018
Last updated
28 May 2026

Browse all Transformers MCQs

Choose the correct answer

Explanation

The no-load test on a transformer is mainly used to determine the magnetizing current, which is the current required to energize the transformer's core. This test does not measure copper losses or overall efficiency directly.