Which of the following statements about Class-Responsibility-Collaborator (CRC) modeling is incorrect?

Software Modelling MCQs for PPSC, FPSC, NTS, and Pakistan government job tests. Select an option below, then read the explanation.

PPSCFPSCNTSPakistan govt jobs
Subject
Software Modellingsoftware-engineering-mcqs › software-modelling
Published
2 Feb 2019
Last updated
28 May 2026

Browse all Software Modelling MCQs

Choose the correct answer

Explanation

The incorrect statement is option C. In a CRC model review, all participants—not just developers—are provided with a subset of the CRC index cards to facilitate thorough evaluation.