Identify the statement that is false regarding start float and finish float.

Construction Planning and Management MCQs for PPSC, FPSC, NTS, and Pakistan government job tests. Select an option below, then read the explanation.

PPSCFPSCNTSPakistan govt jobs
Subject
Construction Planning and Managementcivil-engineering-mcqs › construction-planning-and-management
Published
19 Jan 2019
Last updated
28 May 2026

Browse all Construction Planning and Management MCQs

Choose the correct answer

Explanation

Option A is true: start float and finish float are always equal. Option B is true: total float can be either start float or finish float. Option C is false: start float and finish float must be equal. Option D is true: start float and finish float refer to differences in activity times, not event times.