What is the volume of aggregates needed for a 1 km stretch of water bound macadam road, with a width of 1 meter and a thickness of 10 mm?

Highway Engineering MCQs for PPSC, FPSC, NTS, and Pakistan government job tests. Select an option below, then read the explanation.

PPSCFPSCNTSPakistan govt jobs
Subject
Highway Engineeringcivil-engineering-mcqs › highway-engineering
Published
12 Jan 2019
Last updated
28 May 2026

Browse all Highway Engineering MCQs

Choose the correct answer

Explanation

The quantity of aggregates required for a water bound macadam road measuring 1 kilometer in length, 1 meter in width, and 10 mm in thickness is 12 cubic meters.