In the 'full face' tunneling technique, what is the initial step performed?

Tunnel Engineering MCQs for PPSC, FPSC, NTS, and Pakistan government job tests. Select an option below, then read the explanation.

PPSCFPSCNTSPakistan govt jobs
Subject
Tunnel Engineeringcivil-engineering-mcqs › tunnel-engineering
Published
19 Jan 2019
Last updated
28 May 2026

Browse all Tunnel Engineering MCQs

Choose the correct answer

Explanation

Option A refers to removing the bottom part first, which is incorrect. Option B involves excavating a central drift, which is not the initial step in this method. Option C suggests removing the top portion first, which is also incorrect. The correct approach in the full face method is to begin excavation along the tunnel's perimeter, as stated in option D.