In a PERT/CPM chart, the critical path is determined by connecting events that have which characteristic?

Production Technology MCQs for PPSC, FPSC, NTS, and Pakistan government job tests. Select an option below, then read the explanation.

PPSCFPSCNTSPakistan govt jobs
Subject
Production Technologymechanical-engineering-mcqs › production-technology
Published
27 Jan 2019
Last updated
28 May 2026

Browse all Production Technology MCQs

Choose the correct answer

Explanation

The critical path in a PERT/CPM diagram is identified by linking events with the minimum slack time, as these activities directly affect the project duration.