Which technique is used for project scheduling in software development?

Software Management MCQs for PPSC, FPSC, NTS, and Pakistan government job tests. Select an option below, then read the explanation.

PPSCFPSCNTSPakistan govt jobs
Subject
Software Managementsoftware-engineering-mcqs › software-management
Published
4 Feb 2019
Last updated
28 May 2026

Browse all Software Management MCQs

Choose the correct answer

Explanation

PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method) are both project scheduling techniques suitable for managing software development projects. However, the correct answer here is PERT.