During the time-cost trade-off process in project management, crashing is applied ____________?

Construction Planning and Management MCQs for PPSC, FPSC, NTS, and Pakistan government job tests. Select an option below, then read the explanation.

PPSCFPSCNTSPakistan govt jobs
Subject
Construction Planning and Managementcivil-engineering-mcqs › construction-planning-and-management
Published
19 Jan 2019
Last updated
28 May 2026

Browse all Construction Planning and Management MCQs

Choose the correct answer

Explanation

Crashing is performed on the original critical path activities as well as any activities that become critical as the project is expedited. This is done in order of ascending cost slope to minimize additional expenses while reducing project duration.