Explanation
To find the expected time (TE) and variance for the activity, use the PERT formulas: TE = (Optimistic + 4 × Most Likely + Pessimistic) / 6 and Variance = ((Pessimistic - Optimistic) / 6)². Substituting the values: TE = (2 + 4×3 + 7) / 6 = 5, and Variance = ((7 - 2) / 6)² = (5/6)² = 25/36.
More Construction Planning and Management MCQs
Practice related questions from the same subject.
- 1.What is the minimum required width for fire escape stairways?
- 2.Which of the following statements is incorrect?
- 3.Identify the statement that is false regarding start float and finish float.
- 4.Identify the statement that is incorrect:
- 5.For which type of projects is the PERT network analysis method primarily designed?
- 6.Which of the following statements is accurate regarding CPM network diagrams?
- 7.In PERT analysis, which probability distribution is used to estimate the duration of activities and their likelihood?
- 8.The earliest completion time of an activity is always ____________ compared to the earliest event time of its succeeding node?
More in Civil Engineering Mcqs
- Airport Engineering
- Applied Mechanics and Graphic Statics
- Building Materials and Construction
- Design of Concrete Structures
- Design of Masonry Structures
- Design of Steel Structures
- Dock and Harbor Engineering
- Elements of Remote Sensing
- Engineering Economy
- Environmental Engineering
- Estimating and Costing
- Fluid Mechanics
- Highway Engineering
- Hydraulics and Fluid Mechanics
- Irrigation, Water Resources Engineering and Hydrology
- RCC Structures Design
- Railway Engineering
- Soil Mechanics and Foundation Engineering
- Strength of Materials
- Structural Analysis
- Structural Design Specifications
- Surveying
- Theory of Structures
- Tunnel Engineering
- Waste Water Engineering
- Water Supply Engineering