Time savings in project crashing are achieved by reducing the duration of which type of activity?

Construction Planning and Management MCQs for PPSC, FPSC, NTS, and Pakistan government job tests. Select an option below, then read the explanation.

PPSCFPSCNTSPakistan govt jobs
Subject
Construction Planning and Managementcivil-engineering-mcqs › construction-planning-and-management
Published
19 Jan 2019
Last updated
28 May 2026

Browse all Construction Planning and Management MCQs

Choose the correct answer

Explanation

Time reduction in project crashing is economically beneficial when applied to the cheapest critical activity, as only critical tasks affect the project duration. Crashing non-critical or more expensive critical tasks does not yield cost-effective time savings.