What does the price variation clause in contracts address during the construction phase?

Construction Planning and Management MCQs for PPSC, FPSC, NTS, and Pakistan government job tests. Select an option below, then read the explanation.

PPSCFPSCNTSPakistan govt jobs
Subject
Construction Planning and Managementcivil-engineering-mcqs › construction-planning-and-management
Published
19 Jan 2019
Last updated
28 May 2026

Browse all Construction Planning and Management MCQs

Choose the correct answer

Explanation

The price variation clause is designed to accommodate changes in the costs of essential components, specifically materials, labor, and petrol-oil-lubricant expenses, during construction. It does not cover only specific materials, ad hoc total project cost changes, or the general inflation rate alone.