In PERT analysis, the critical path is determined by connecting events that have which type of slack?

Production Technology MCQs for PPSC, FPSC, NTS, and Pakistan government job tests. Select an option below, then read the explanation.

PPSCFPSCNTSPakistan govt jobs
Subject
Production Technologymechanical-engineering-mcqs › production-technology
Published
27 Jan 2019
Last updated
28 May 2026

Browse all Production Technology MCQs

Choose the correct answer

Explanation

The critical path in PERT is formed by linking events with zero slack, meaning there is no delay allowed without affecting the overall project duration. Positive slack indicates extra time, negative slack suggests a delay, dummy tasks are placeholders, and key activities are important but not necessarily on the critical path.